Web versions of Project Management Tool

Hello, Could I get the list of Project Management related applications that are accessible via WEB. I have access to an online project management related tool called MS Planner. However this is not suitable to my needs. It lacks the most basic…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-15T22:18:20.53+00:00
Ramesh Errabolu 0 Reputation points
commented 2025-12-15T23:53:32.35+00:00
Dale Howard [MVP] 29,825 Reputation points MVP Volunteer Moderator
3 answers

Planner and Project Plan 3 - sort activities by start date, end date, float, ...

In Planner and Project Plan 3, I need to sort activities in the Timeline barchart so they display in Start Date then End Date order. How can I do this? Moderator remove personal information

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-12T08:44:57.1533333+00:00
Christopher Morley 0 Reputation points
commented 2025-12-14T14:44:55.4566667+00:00
Allison-H 5,040 Reputation points Microsoft External Staff Moderator
3 answers

MS Project : Can't use Resource Pool

Hi, I have (according to Help | About): Microsoft® Project® Online Desktop Client MSO (Version 2511 Build 16.0.19426.20186) 64-bit I created a resource pool .mpp file and a "task only" .mpp file. They are both saved in the same dir. I have them…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-11T00:05:38.62+00:00
Jim Lee 0 Reputation points
answered 2025-12-13T03:36:33.4433333+00:00
Vivian-HT 9,315 Reputation points Microsoft External Staff Moderator
1 answer

Premium and basic account and cannot create "checklist"

I didn't see a child tag for planner, so selected project. I have both a premium and basic account and cannot create "checklist" in either license. I also know that the feature for "add to card" is not accessible to…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-11T14:46:23.15+00:00
Cynthia Marsh (Dragonfly) 0 Reputation points
commented 2025-12-12T16:33:51.91+00:00
Vy Nguyen 7,845 Reputation points Microsoft External Staff Moderator
0 answers

Planner and Project Plan 3 - wrap text

In Planner and Project Plan 3, in the Timeline report, how can I wrap the text in the task description so I can see the full descriotion on multiple lines? AT the moment this is truncated so I can only see the first few characters of the…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-12T08:49:56.8166667+00:00
Christopher Morley 0 Reputation points
commented 2025-12-12T08:56:49.02+00:00
Nam-D 735 Reputation points Microsoft External Staff Moderator
1 answer

Planner and Project Plan 3 - print Timeline

In Planner and Project Plan 3 I need to print Timeline reports as my client wants to see them on paper. How can I do this? Chris Morley

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-12T08:47:17.5933333+00:00
Christopher Morley 0 Reputation points
commented 2025-12-12T08:56:24.6566667+00:00
Nam-D 735 Reputation points Microsoft External Staff Moderator
2 answers

Error when adding or editing tasks in Grid View – D365 Project Operations

Hi everyone, I’m currently migrating all of our PMO data into Dynamics 365 Project Operations. I have a project set up and have been creating and editing tasks in Grid View without any issues for the past four weeks. However, today I started seeing the…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-09T15:49:14.48+00:00
Jeff Barker 0 Reputation points
commented 2025-12-11T18:30:07.0033333+00:00
Alexis-NG 9,435 Reputation points Microsoft External Staff Moderator
3 answers

MS Project with site needs to become master project, but the subproject button is grayed out.

Hello, I have the following problem: I have created SharePoint site with task list from PWA. Then I used open with MS Project and made many modifications on the project. At some point I decided I need a subproject, but the button is grayed out. I have…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-11T12:53:58.21+00:00
Stoyan Ivanov 5 Reputation points
edited an answer 2025-12-11T14:05:58.6566667+00:00
Tamara-Hu 8,635 Reputation points Microsoft External Staff Moderator
5 answers

How do I remove the following sentence from my Microsoft Survey "when you submit this form, it will not automatically collect your details like name and email address unless you provide it yourself"?

When I send out a Microsoft Survey, the recipients always have the following sentence in their survey: "When you submit this form, it will not automatically collect your details like name and email address unless you provide it yourself." How…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-07-03T13:32:42.7366667+00:00
Carrington, Patrick J (PERS) 15 Reputation points
commented 2025-12-11T09:05:27.01+00:00
Stine Goldbach 0 Reputation points
1 answer

Unable to purchase an additional license for Project Plan 3. Increase from 2 licences to 3

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-09T03:04:47.5833333+00:00
Travis Banks 0 Reputation points
commented 2025-12-10T11:37:13.3766667+00:00
AlexDN 7,440 Reputation points Microsoft External Staff Moderator
2 answers

Can Schedule Board in Project Operations be used as a team calendar?

Hi Everyone, We’re setting up a new Project Operations environment for our SaaS department and want to know if the Schedule Board can function as a shared team calendar. Currently, we use Outlook shared calendars, which work well, but we’d like to…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-08T12:18:39.5433333+00:00
Jeff Barker 0 Reputation points
commented 2025-12-09T15:46:26.1733333+00:00
Tina L 8,820 Reputation points Microsoft External Staff Moderator
2 answers

MS Projects - CTRL + (direction) Arrow combination doesnt work

I have been running into weird issue with Microsoft Projects 2024 where nudging doesn't work on my .mpp files. Specifically in Network diagram if I am in Gantt chart then CTRL+Arrow functions fine. It was last working around mid November. I have asked…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-04T13:32:29.02+00:00
SP10 0 Reputation points
commented 2025-12-07T15:05:59.35+00:00
Tina L 8,820 Reputation points Microsoft External Staff Moderator
2 answers

Finish date is not moving out when I increase the duration in MS Project 365

Why isn't the finish date moving out when I increase the duration in MS 365?

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-04T22:15:43.11+00:00
mich fuert 0 Reputation points
commented 2025-12-07T00:24:33.8333333+00:00
Jeanie H 7,850 Reputation points Microsoft External Staff Moderator
2 answers One of the answers was accepted by the question author.

is Business Central compatible with MS project?

can BC be set up to automatically exchange data with MS project? Moved from: Microsoft 365 Insider | Project | Windows

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-01T22:48:47.5033333+00:00
Claus Horny 40 Reputation points
accepted 2025-12-04T20:45:17.39+00:00
Claus Horny 40 Reputation points
2 answers

Planner access issue

I have created a shared Planner but now can no longer access. I've checked with all other team members and everyone is receiving the same error. Correlation ID: [Moderator note: personal information removed]

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-02T15:22:46.01+00:00
Chris Stanton 0 Reputation points Microsoft Employee
commented 2025-12-03T21:47:06.9733333+00:00
Jay Tr 6,460 Reputation points Microsoft External Staff Moderator
2 answers

Migration Plan Assistance from Microsoft Support

Currently we're using go daddy Microsoft 365 plan so we're planning directly to use from Microsoft. We have 90+ user's we need to buy separate Domain and migrate all the email id and setup authenticator for logging in.We have 3 TB data from OneDrive and…

Microsoft 365 and Office | Project | For business | Windows
asked 2024-04-05T18:08:47+00:00
Anonymous
edited the question 2025-12-03T14:13:11.2066667+00:00
Don Varnau 19,545 Reputation points Volunteer Moderator
2 answers One of the answers was accepted by the question author.

can you create a schedule in BC

what is the schedule functionality in BC compared to MS project? Moved from: Microsoft 365 Insider | Project | Windows

Microsoft 365 and Office | Project | For business | Windows
asked 2025-12-01T22:54:02.91+00:00
Claus Horny 40 Reputation points
commented 2025-12-03T13:49:34.43+00:00
AlexDN 7,440 Reputation points Microsoft External Staff Moderator
1 answer

How do I get my Microsoft Project to work on my new laptop?

How do I get my Microsoft Project to work on this new laptop. I had bought it for my old one, but after all the scanning that was done to get everything I had on the old to the new, the Microsoft Project that I had won't work on the new one.

Microsoft 365 and Office | Project | For business | Windows
asked 2025-11-29T22:18:32.8133333+00:00
Frank Dickinson 0 Reputation points
commented 2025-12-01T06:53:37.2266667+00:00
Vivian-HT 9,315 Reputation points Microsoft External Staff Moderator
2 answers

People Picker in Project Detail Pages - Not Working for Already Created Projects

Hi, I have a non-mandatory field ("Expert") in PDP. When I create a new project, I can select the "Expert" using People Picker. When I try to open an existing project (to assign/reassign an Expert) the People Picker feature does not…

Microsoft 365 and Office | Project | For business | Windows
asked 2025-11-24T18:02:31.5233333+00:00
Anil Bhatia (Consultant) 0 Reputation points
edited an answer 2025-11-26T18:09:35.6033333+00:00
Hendrix-C 8,650 Reputation points Microsoft External Staff Moderator
2 answers

How to Add MS Project to the 365 plan

How do I add MS Project to an existing MS365 account

Microsoft 365 and Office | Project | For business | Windows
asked 2025-11-20T23:49:28.8633333+00:00
Manly Maintenance 0 Reputation points
commented 2025-11-24T06:35:06.75+00:00
Vivian-HT 9,315 Reputation points Microsoft External Staff Moderator