In Microsoft Planner, sorting activities in the Timeline view by Start Date and End Date is not directly supported as a built-in feature. However, you can manage tasks and their dates effectively by ensuring that each task has the appropriate Start Date and Due Date set.
To achieve a similar effect, you can:
- Set Start Dates: Make sure each task has a defined Start Date. This will help in visually organizing tasks in the Timeline view.
- Use Due Dates: Set Due Dates for tasks as well. Although Planner does not allow sorting directly by these dates, having them set will help you manage and visualize timelines better.
- Check Plan Views: If you have access to advanced capabilities with a Project Plan 3 license, you may have additional features that could assist in managing and visualizing tasks more effectively.
For more advanced project management features, consider using Microsoft Project, which offers more robust sorting and filtering options for tasks based on various criteria, including Start Date and End Date.